--- title: "How does Quickbase calculate the start date of a dependent task?" slug: "how-does-quickbase-calculate-the-start-date-of-a-dependent-task" updated: 2026-04-29T17:00:36Z published: 2026-04-29T17:00:36Z canonical: "help.quickbase.com/how-does-quickbase-calculate-the-start-date-of-a-dependent-task" --- > ## Documentation Index > Fetch the complete documentation index at: https://help.quickbase.com/llms.txt > Use this file to discover all available pages before exploring further. # How does Quickbase calculate the start date of a dependent task? Quickbase calculates the start date of a dependent task based on a full day and, by default, a five-day work week. For example, if Task 1 will take 2.5 days to complete and it begins on 10-16-2003, it will end on 10-20-2003 (instead of 10-18-2003) because weekends aren't included in the calculation. This means that if Task 2 is dependent on Task 1 finishing, then the start date for Task 2 will be 10-20-2003 beginning at midday.