New Task Scheduler: Optimize a Schedule

Prev Next

Note

The New Task Scheduler is in beta, so to turn it on for your account, contact FastField Support.

Optimize Schedule plans a day or a week for you, then you review the plan and send it to your technicians. This article covers how to run Optimize, read the results, adjust the plan, and save and dispatch it.

How Optimize works

Optimize places unscheduled tasks into your technicians' routes. It aims for the shortest travel time, and it weighs:

  • Working hours and time off, so work lands only when a technician is available

  • Skills, preferring technicians who hold the skills a task requires

  • Location, with each technician's home base and the drive between stops

  • Time windows, which are always met when required and met when possible when preferred

  • Locks on tasks already on the board

Optimize plans only what's on screen: the day in the Day view, or the week in the Week view. It plans from now on, so nothing is placed or moved in time that has passed. It only plans for the technicians the board shows.

The results are proposals. Nothing is sent to technicians until you select Save & Dispatch.

Note

Optimize is part of the Pro Plan. Account admins and Dispatchers can run it from the Schedule view.

Important

Skills guide Optimize, but they don't block it. When no qualified technician is free, Optimize can still assign a task to someone without the skill. The board then shows a skill warning on the task. Check for warnings before you save.

Which settings apply depends on Account > Company Settings > General > Scheduling: Use availability when scheduling, Use skills when scheduling, and Use location when scheduling.

Before you optimize

  • Go to the day or week you want to plan.

  • Filter the board to the technicians who should get work. To learn how, see New Task Scheduler: The Schedule View.

  • Unlock any dispatched task the optimizer may move. Every task on the board starts locked.

A dispatched task's padlock set to Time unlocked before optimizing

Run Optimize

  1. On the Schedule view, select Optimize Schedule.

The Optimize Schedule button

  1. Under Tasks to schedule, choose one:

    • All unscheduled: every task in the Unscheduled Tasks panel

    • Selected only: the tasks you checked in the Unscheduled Tasks panel, plus any unlocked tasks on the board

  2. Check the Scheduling Horizon. It shows the day or week on screen, and the part that's already passed.

  3. Check the technicians. Optimize includes everyone the board shows who has working hours.

  4. Leave Objective set to Minimize travel time.

  5. Select Run Optimization.

The Optimize schedule dialog for one day, with the technicians and the objective

Minimize travel time is the only objective you can choose for now.

The dialog also warns you about tasks Optimize can't move or can't use:

  • In-progress tasks can't be moved, because the technician is already on site.

  • Unlocked dispatched tasks may be reassigned.

  • Location outliers, far outside your usual operating area, are left out.

  • Technicians with no working hours on those days don't get work.

The Optimize schedule dialog for a week, with an unlocked dispatched task listed

While Optimize runs, the dialog shows each step. To stop, select Cancel run. A large run can take several minutes. Keep the tab open, because the result comes back to that page.

Review the results

When Optimize finishes, the dialog shows a summary:

  • Scheduled: unscheduled tasks it placed on the schedule

  • Moved: unlocked tasks it gave a new time or technician

  • Unchanged: tasks it kept exactly where they were

  • Could Not Schedule: tasks it couldn't place

  • Driving: the total drive time

Each scheduled task shows its technician, the stop before it, the drive, the date, the arrival time, and the duration.

The results of a week's optimization, with the summary and the scheduled tasks

Select Done to see the plan on the board. Tasks Optimize placed are marked as proposed, and they're unlocked, so a later run may change them.

The Week view after optimizing, with the proposed tasks on each technician's row

Tasks that couldn't be scheduled

Each task under Could Not Schedule stays in the Unscheduled Tasks panel, with the reason it wasn't placed. Common reasons include:

  • A required window on another day. Select Go to that day to optimize it there.

  • A required window that misses every shift. Widen the window or switch it to Preferred.

  • A task too long for its required window. The task can't finish within the window before the shift ends.

  • No working hours. No technician works when the task could be done.

  • Too far from every home base. The round trip is longer than the shift.

  • Everyone is fully booked. All qualified technicians are full.

  • No room in any route. Optimize couldn't fit the task into any technician's day.

A 4-hour task that couldn't be scheduled in its 2-hour required window

The stats bar also shows how many tasks the last run couldn't place. Select it to see their names.

Adjust the plan

Before you save, check the board and make any changes by hand:

  • Hover over tasks with a warning icon, such as a missing skill.

  • Drag a task to another time or technician.

  • Drag a task back to the Unscheduled Tasks panel to leave it unassigned.

  • Lock tasks you're happy with, and run Optimize again for the rest.

  • Select Undo to go back a step.

An optimized task assigned to a technician without the required skill

To start over, select Discard Changes. The board goes back to what was last saved.

Save and dispatch

  1. Select Save & Dispatch.

The Review Changes dialog lists every change, grouped as New Assignments, Reassignments, Retimed, and Back to Queue. Each row shows the technician, time, location, and any warnings.

The Review Changes dialog, with new assignments and skill warnings

  1. Read the warnings. If a change leaves a serious conflict, check the box to acknowledge it, or select Acknowledge all unresolved conflicts.

  2. To email the technicians, select Email technicians receiving work, Email technicians losing work, or both.

  3. Select Confirm & Save.

The tasks are saved and sent:

  • A technician who gets a new or reassigned task receives a push notification in the FastField mobile app.

  • A task that only changes time stays on the same technician's device, so no push is sent.

  • A task taken off a technician leaves their app the next time it syncs.

  • Emails go out only if you checked an email option.

Saved tasks show as Dispatched on the board, and they're locked again.

The Day view after saving, with every task dispatched

Save one day or a whole week

Save & Dispatch saves the changes on screen and on any other day with unsaved changes. The review says how many changes it saves, and on which days.

  • In the Day view, to save only that day, select the arrow next to Save & Dispatch, and then select Save only that day.

  • In the Week view, to save only that week, select the arrow, and then select Save only this week.

The arrow appears only when the day or week on screen and other days both have changes.

Note

The review checks for conflicts only on the days on screen. Changes on other days are saved as you left them.

What's next